Remove weekends from Burndown in Board View (TFS 2012 - Scrum 2.0)
Asked Answered
D

1

72

I would like to modify the Burndown chart in TFS 2012's Scrum 2.0 Template so that weekends no longer show. I've already looked at this article, but unfortunately the solution listed there doesn't apply to the Burndown Chart when running from Board View.

example

Does anyone have a suggestion for how I can modify it in Board View?

Dungdungan answered 11/2, 2013 at 18:46 Comment(7)
You can modify only report to exlude non-working days. TFS2012 update1 didn't fix this for Board view. Looking forward to Microsoft and still waiting...Fullgrown
visualstudio.uservoice.com/forums/121579-visual-studio/… It is planned to change this in some future update.Koreykorff
You've got to be kidding me? This is very non-extensible for being a...template. How embarrassing Microsoft!Estevan
This is fixed in update 3 and future versions.Kowal
I don't think it has Andrew, unless I'm missing something. I've just installed Update 3 and can't see any change with the Burndown Board View.Dumont
Sadly it didn't make it into the TFS 2013 RTM :(Aspergillus
Apparently solved as from today! visualstudio.com/news/2014-jan-22-vsoCircuit
H
8

UPDATE: The burndown excludes the weekends on Visual Studio Online. Later this year, this feature ships with TFS 2013 Update 2 for on-prem customers.

See the announcement at http://www.visualstudio.com/news/2014-jan-22-vso.

If you want to configure the working days of your team, you can click on the gear button in the top right corner which will open the admin area in a new tab. Click on your team, and choose the “settings” tab.

The TFS team on uservoice explained recently that they started working on this feature request Burndown chart should exclude non-work days.

Hurlow answered 12/9, 2013 at 16:7 Comment(0)