How do you estimate a ROI for clearing technical debt?
Asked Answered
G

7

20

I'm currently working with a fairly old product that's been saddled with a lot of technical debt from poor programmers and poor development practices in the past. We are starting to get better and the creation of technical debt has slowed considerably.

I've identified the areas of the application that are in bad shape and I can estimate the cost of fixing those areas, but I'm having a hard time estimating the return on investment (ROI).

The code will be easier to maintain and will be easier to extend in the future but how can I go about putting a dollar figure on these?

A good place to start looks like going back into our bug tracking system and estimating costs based on bugs and features relating to these "bad" areas. But that seems time consuming and may not be the best predictor of value.

Has anyone performed such an analysis in the past and have any advice for me?

Garcia answered 24/11, 2009 at 14:29 Comment(0)
U
8

Managers care about making $ through growth (first and foremost e.g. new features which attract new customers) and (second) through optimizing the process lifecycle.

Looking at your problem, your proposal falls in the second category: this will undoubtedly fall behind goal #1 (and thus get prioritized down even if this could save money... because saving money implies spending money (most of time at least ;-)).

Now, putting a $ figure on the "bad technical debt" could be turned around into a more positive spin (assuming that the following applies in your case): " if we invest in reworking component X, we could introduce feature Y faster and thus get Z more customers ".

In other words, evaluate the cost of technical debt against cost of lost business opportunities.

Uribe answered 24/11, 2009 at 14:41 Comment(4)
(+1) I did something like this one time. I basically looked at customer needs we would not be able to meet if we did not handle current technical debt. I also demonstrated one new feature (one I was able to introduce quickly) and show how I could do more if I could refactor and rearchitect the source. It worked very well and the resulting program was much better and both customers and internal users were/are happy with the result.Welbie
@jason: exactly! It is always easier to have "bad news" absorbed by putting a "positive spin" on the situation... turn the table around!Uribe
I see, so you're saying I should get a look at our product's roadmap (which should have an estimated ROI for each feature). Then estimate how much clearing the technical debt would affect that future feature's ROI and report on that?Garcia
@SteveWilkins: that's what I am suggesting yes: if you can make a positive case for "clearing some technical debt" then it will appeal more to the managers. You will have a hard time otherwise: just putting on the table "bad news" won't do you good. Always find a positive spin... well at least, that's my contribution to your question :-)Uribe
Y
3

I think you're on the right track.

I've not had to calculate this but I've had a few discussions with a friend who manages a large software development organisation with a lot of legacy code.

One of the things we've discussed is generating some rough effort metrics from analysing VCS commits and using them to divide up a rough estimate of programmer hours. This was inspired by Joel Spolsky's Evidence-based Scheduling.

Doing such data mining would allow you to also identify clustering of when code is being maintained and compare that to bug completion in the tracking system (unless you are already blessed with a tight integration between the two and accurate records).

Proper ROI needs to calculate the full Return, so some things to consider are: - decreased cost of maintenance (obviously) - opportunity cost to the business of downtime or missed new features that couldn't be added in time for a release - ability to generate new product lines due to refactorings

Remember, once you have a rule for deriving data, you can have arguments about exactly how to calculate things, but at least you have some figures to seed discussion!

Yarndyed answered 24/11, 2009 at 14:42 Comment(3)
Can you elaborate on how you can generate an effort estimate based on the commits? Is it something like the time difference between commit A and commit B by developer X is the rough effort on commit B?Garcia
Yes, (I did say "rough") - simply review commit times by known working days.Yarndyed
On a large code base with long history, statistical approaches like this should converge on reasonable estimates. You do, of course, need to know to what degree people could devote time to a project but that's a simple time-series analysis and can be refined when people look at the figures. ("Hey, I was on holiday for that week and working 30 hours/week on FizzBuzz 2.0 in May").Yarndyed
A
2

Sonar has a great plugin (technical debt plugin) to analyze your sourcecode to look for just such a metric. While you may not specifically be able to use it for your build, as it is a maven tool, it should provide some good metrics.

Here is a snippet of their algorithm:

Debt(in man days) =
    cost_to_fix_duplications +
    cost_to_fix_violations + 
    cost_to_comment_public_API +
    cost_to_fix_uncovered_complexity + 
    cost_to_bring_complexity_below_threshold


 Where :

 Duplications = cost_to_fix_one_block * duplicated_blocks

 Violations   = cost_to fix_one_violation * mandatory_violations

 Comments     = cost_to_comment_one_API * public_undocumented_api

 Coverage     = cost_to_cover_one_of_complexity * 
                         uncovered_complexity_by_tests (80% of
                         coverage is the objective)

 Complexity   = cost_to_split_a_method *
                         (function_complexity_distribution >=
                          8) + cost_to_split_a_class *
                         (class_complexity_distribution >= 60)
Amnesty answered 24/11, 2009 at 14:44 Comment(0)
F
2

I can only speak to how to do this empirically in an iterative and incremental process.

You need to gather metrics to estimate your demonstrated best cost/story-point. Presumably, this represents your system just after the initial architectural churn, when most of design trial-and-error has been done but entropy has had the least time to cause decay. Find the point in the project history when velocity/team-size is the highest. Use this as your cost/point baseline (zero-debt).

Over time, as technical debt accumulates, the velocity/team-size begins to decrease. The percentage decrease of this number with respect to your baseline can be translated into "interest" being paid on each new story point. (This is really interest paid on technical and knowledge debt)

Disciplined refactoing and annealing causes the the interest on technical debt to stablize at some value higher than your baseline. Think of this as the steady-state interest the product owner pays on the technical debt in the system. (The same concept applies to knowledge debt).

Some systems reach the point where the cost + interest on each new story point exceeds the value of the feature point being developed. This is when the system is bankrupt, and it's time to rewrite the system from scratch.

I think it's possible to use regression analysis to tease apart technical debt and knowledge debt (but I haven't tried it). For example, if you assume that technical debt correlates closely with some code metrics, e.g. code duplication, you could determine the degree the interest being paid is increasing because of technical debt versus knowledge debt.

Foursquare answered 24/11, 2009 at 17:16 Comment(0)
B
1

+1 for jldupont's focus on lost business opportunities.

I suggest thinking about those opportunities as perceived by management. What do they think affects revenue growth -- new features, time to market, product quality? Relating debt paydown to those drivers will help management understand the gains.

Focusing on management perceptions will help you avoid false numeration. ROI is an estimate, and it is no better than the assumptions made in its estimation. Management will suspect solely quantitative arguments because they know there's some qualitative in there somewhere. For example, over the short term the real cost of your debt paydown is the other work the programmers aren't doing, rather than the cash cost of those programmers, because I doubt you're going to hire and train new staff just for this. Are the improvements in future development time or quality more important than features these programmers would otherwise be adding?

Also, make sure you understand the horizon for which the product is managed. If management isn't thinking about two years from now, they won't care about benefits that won't appear for 18 months.

Finally, reflect on the fact that management perceptions have allowed this product to get to this state in the first place. What has changed that would make the company more attentive to technical debt? If the difference is you -- you're a better manager than your predecessors -- bear in mind that your management team isn't used to thinking about this stuff. You have to find their appetite for it, and focus on those items that will deliver results they care about. If you do that, you'll gain credibility, which you can use to get them thinking about further changes. But appreciation of the gains might be a while in growing.

Bondstone answered 24/11, 2009 at 15:4 Comment(0)
C
0

Being a mostly lone or small-team developer this is out of my field, but to me a great solution to find out where time is wasted is very, very detailed timekeeping, for example with a handy task-bar tool like this one that can even filter out when you go to the loo, and can export everything to XML.

It may be cumbersome at first, and a challenge to introduce to a team, but if your team can log every fifteen minutes they spend due to a bug, mistake or misconception in the software, you accumulate a basis of impressive, real-life data on what technical debt is actually costing in wages every month.

The tool I linked to is my favourite because it is dead simple (doesn't even require a data base) and provides access to every project/item through a task bar icon. Also entering additional information on the work carried out can be done there, and timekeeping is literally activated in seconds. (I am not affiliated with the vendor.)

Commutate answered 24/11, 2009 at 14:42 Comment(0)
B
0

It might be easier to estimate the amount it has cost you in the past. Once you've done that, you should be able to come up with an estimate for the future with ranges and logic even your bosses can understand.

That being said, I don't have a lot of experience with this kind of thing, simply because I've never yet seen a manager willing to go this far in fixing up code. It has always just been something we fix up when we have to modify bad code, so refactoring is effectively a hidden cost on all modifications and bug fixes.

Brominate answered 24/11, 2009 at 14:48 Comment(0)